Advantage Austria Show navigation

Karachi Electric Supply Company launches first phase of GE Jenbacher 180MW power plant

electricity © photocase.com/NormanBates

© photocase.com/NormanBates

5. June 2009

Austrian supplier signed deal with KESC for the replacement of the existing plant to a new more powerful 180MW plant

The first test operations of a 21 MW gas staion in Site launched the first phase of the new power plant. The $ 53 million project will be carried out in four phases with completion slated for July 2009.

The new plant will replace the engines of an existing power plant which have completed their planned life span and will be working at up to 40 percent effiency. Thr project will be completed in record time to hit peak summer demand.

print